The project plan will be developed in order to conduct the research to identify the positive economic, cultural, and ethical impacts of globalisation on different business functions within organisations. The project will include the research related to topic and analyse the data collected related to the topic of the research. The activities of the project will be undertaken within the estimated cost and time for the project[ CITATION Mar185 \l 1033 ]. The goals of the project are to identify the effect of the globalization upon the organizations in context to the areas that our business economics, culture, and ethics. The information related to the research topic will be delivered as a deliverable on the right time.
The milestones of the project are
Milestone | Description | Delivery Date |
Business Case Approval | The Business Case has been documented and was approved by the Project Sponsor. | 08/11/2018 |
project charter approval
| The project charter has been documented and was approved by the project sponsors | 30/11/2018 |
project plan approval | the project plan has been documented and was approved by the high management of the project | 18/01/2019 |
selection of the sources for the secondary research | the selection of the appropriate sources of the secondary research by the project team and approved by the project manager | 19/02/2019 |
[ CITATION Jas18 \l 1033 ]
The main phases of the project are the project initiation phase, the project budget planning phase, the project execution phase and project closure phase.
Phase | Description© | Sequence |
Project Initiation
| The initiation phase will include defining the process for gathering the requirements, requirement analysis, creating requirement documents, project charter development, project scope definition, estimates of time, cots and resources, list of key stakeholders and project charter approval | Phase # 1 |
Project Planning
| Project Plan development, scope statements, WBS, Performance baseline measurements project schedule plan, Resource management, supporting FM process plans and Project plan approval are included in the project planning phase. | Phase # 2 |
Project Execution
| Conducting secondary research and selecting the sources for the secondary research are included in the execution phase of the project. | Phase # 3 |
Project Clsure | Contract closure, launching project lesson learned reviews, establishing process for archiving the project docs, archiving documents and conducting administrative closeout are included in the project closure phase. | Phase # 4 |
[ CITATION Rob15 \l 1033 ][ CITATION Bis181 \l 1033 ]
The major project activities are:
Phase | Activity | Description© | Sequence |
project initiation
| project charter development
| The project charter is produced in order to state the objectives of the project which includes the goals of the project, responsibilities and goals, identification of the main stakeholders and the authority of the project manager. | After defining the process for gathering requirements but before the business case aproval. |
Project Planning | Work Break down structure | The work break down structure is developed considering all the phases of the project. It will help in demonstrating the sequences of the activities of the project in a simple manner. | It should be developed after developing the scope statement and before resource management. |
Project Execution | Collecting the secondary data | The secondary data should be collected from different sources in order to meet the objectives of the research project. | It should be done before the analysis of the research data to meet objectives and after selecting the secondary data sources. |
Project Closure | Archive documents
| The archiving of the documents is important in order keep the records of the documents of the research project | it should be done before conducting administrative closeout and after establishing the process for archiving the project docs. |
[ CITATION Ric18 \l 1033 ]
Phase | Activity | Task | Sequence |
Project Planning | Project Plan development | Explaining project plan to key stakeholders Define roles and responsibilities Develop a Scope Statement. Develop the schedule and cost baselines | 1st
2nd 3rd 4th |
Project Execution | Conducting secondary research | identifying subject domain identifying sources to acquire the information Gathering existing data Comparing the data from the different sources Analyzing the data | 1st 2nd
3rd 4th
5th |
Project closure
| Contract closure | accepting all work monitoring work lists for ensuring their completion paying all bills | 1st 2nd
3rd |
[ CITATION Wri182 \l 1033 ]
Task© | Effort |
Explaining project plan to key stakeholders Define roles and responsibilities Develop a Scope Statement. Develop the schedule and cost baselines | 2 days 2 days 2 days 5 days |
identifying subject domain identifying sources to acquire the information Gathering existing data Comparing the data from the different sources Analyzing the data | 5 days 4 days 5 days 8 days 7 days |
accepting all work monitoring work lists for ensuring their completion paying all bills | 2 days 7 days 3 days |
[ CITATION Pro185 \l 1033 ]
Task© | Resource |
Explaining project plan to key stakeholders Define roles and responsibilities Develop a Scope Statement. Develop the schedule and cost baselines | Project manager Project manager Project manager and project team Project manager and project team |
identifying subject domain identifying sources to acquire the information Gathering existing data Comparing the data from the different sources Analyzing the data | Project manager and project team Project manager and project team Project team Project team Project manager and project team |
accepting all work monitoring work lists for ensuring their completion paying all bills | Project manager Project manager Project manager and project team |
[ CITATION Wri183 \l 1033 ]
The following are the major dependencies in the project in order to accomplish the activities of the project in an efficient manner within the estimated time and schedule.
Activity | Depends on© | Dependency Type |
project charter development | Create requirements documents | Finish-to-start |
establish high level time, cost and resources estimates | project scope definition | Finish-to-start |
WBS | Project Plan development | Finish-to-finish |
Meeting the requirements of the research through analyzing the collected data | Collecting the secondary data | Finish-to-start |
conduct administrative closeout | Archive documents
| Finish-to-finish |
[ CITATION Pro186 \l 1033 ]
1. All the activities related to the project will be accomplished within the estimated time and budget.
2. The project team will be responsible for making sure that the approval from the sponsors, management and the project manager is obtained on the right time.
3. The planning of the activities of the project will be undertaken by the project team and the approval from the project manager will be obtained after the development of project plan document[ CITATION Fah12 \l 1033 ].
The identified constraints in the project are:
1. The project team should complete the activities of the project on time in order to deliver the complete project on time.
2. All the activities should be completed by the project team within the available budget.
3. The project manager should analyse the performance of the project in order to meet the objectives of the project[ CITATION Mar186 \l 1033 ].
1. Wrike, 2018. What is a Task in Project Management?.[Online] Available at:https://www.wrike.com/project-management-guide/faq/what-is-a-task-in-project-management/
[Accessed 2018]
2. Bisk, 2018. Five Phases of the Project Management Lifecycle.[Online]
Available at:https://www.villanovau.com/resources/project-management/5-phases-project-management-lifecycle/#.W7W7rtcza1s
[Accessed 2018].
3. Project Insight, 2018. Understanding Task Dependencies in Project Management.[Online]
Available at:https://www.projectinsight.net/project-management-basics/task-dependencies
[Accessed 2018].
4. Project Management Knowledge management, 2018. Effort.[Online] Available at:https://project-management-knowledge.com/definitions/e/effort/
[Accessed 2018].
5. Robin Brady, 2015. ADMINISTRATIVE CLOSURE VS. CONTRACT CLOSURE.[Online]
Available at:https://community.simplilearn.com/threads/administrative-closure-vs-contract-closure.421/
[Accessed 2018].
6. Rouse, M., 2018. constraint (project constraint).[Online] Available at:https://whatis.techtarget.com/definition/constraint-project-constraint
[Accessed 2018].
7. Rouse, M., 2018. project scope.[Online] Available at:https://searchcio.techtarget.com/definition/project-scope
8. Suttle, R., 2018. Major Activities in Project Management Phases.[Online]
Available at:https://smallbusiness.chron.com/major-activities-project-management-phases-35964.html
[Accessed 2018].
9. Usmani, F., 2012. Assumptions and Constraints in Project Management.[Online]
Available at:https://pmstudycircle.com/2012/10/assumptions-and-constraints-in-project-management/
[Accessed 2018].
10. Westland, J., 2018. What Are Milestones in Project Management?.[Online]
Available at:https://www.projectmanager.com/blog/milestones-project-management
[Accessed 2018].
11. Wrike, 2018. What is a Resource in Project Management?.[Online]
Available at:https://www.wrike.com/project-management-guide/faq/what-is-a-resource-in-project-management/
[Accessed 2018].